Updated On: 05 December, 2023 07:11 AM IST | Mumbai | Prajakta Kasale
Pumping out water from conduit, which was leaking in multiple spots, while preventing landslides at excavated spot posed challenge to civic body team

Workers carry out repairs on the 1,800-mm-diameter pipeline at Andheri East
After four days, the Brihanmumbai Municipal Corporation (BMC) has finished repairing the large pipeline that supplies water to lakhs of residents in Andheri, Vile Parle, Santacruz, Khar, Ghatkopar and Kurla. The supply of water resumed late on Monday evening but water pressure is expected to be low for at least a week. Residents have demanded action against those responsible for damaging the pipe.
On Thursday, the 1,800-mm-diameter water line near Seepz Gate No. 3 and Indian Oil Petrol Pump at Andheri East was damaged at multiple points while drilling work of the Metro 6 line was in progress. After temporary repair work was carried out, the BMC began fixing the line on Saturday morning and the work was expected to be completed by 8.30 am on Sunday. However, the work was completed by 1 pm on Monday. The water supply to some spots was supposed to resume by 6 pm but Andheri and Khar were the first to receive water about an hour later.