Updated On: 08 November, 2022 08:05 AM IST | Mumbai | Rajendra B. Aklekar
After reports that highlighted issue, MRVC completed facilities, also connecting a link way to new footbridge at Charni Road station, before stipulated period

The MRVC built the new staircase
Western Railway on Monday evening opened the new north-end staircase at Charni Road station in 28 days since they closed the old one. mid-day had been pursuing the issue diligently, highlighting the great inconvenience the closed staircase had caused local residents and regular commuters.
The Mumbai Railway Vikas Corporation’s (MRVC) target for a linkway and the staircase was about 50 days.