Nahur Bridge widening work: 'It was challenging to place girder'

Railways use unique pulley and winch method to place girder to dodge water pipeline that runs dangerously close

Listen to this article :
The work on the Nahur bridge was challenging, making the railways prepare for it for the past six months

The work on the Nahur bridge was challenging, making the railways prepare for it for the past six months

Work on the first phase of widening of Nahur bridge over railway lines was completed in an operation on Saturday night. Railway officials said the work to install the girders was challenging due to lack of space in view of a water pipeline close to the site and the narrow road below. To ensure placing the girders safely, officials prepared for six months to work out a unique method. Bridge work is likely to be completed before the monsoon. 

The Nahur road overbridge, which originally had four lanes, will get two new lanes on either side, as per the plans. However, as the bridge runs over railway tracks and several utilities needed to be shifted for the extensions, the railway officials had to plan a process to install the girders without inconveniencing train or traffic movement. 