Updated On: 05 December, 2022 05:46 AM IST | Mumbai | Rajendra B. Aklekar
Railway officials say the work of roof tiles and planks replacement is currently underway

The original roof of Bandra station had been made in England
The work on the conservation, restoration and upgradation of grade-1 heritage structure of Bandra station has now entered the second phase and is likely to be completed by January 2023. A senior official said that the work of roof and other elements is now on and the overall cost of the project is Rs 10.32 crore. It will restore Bandra station back to its yesteryear glory.
“The work includes roof tiles and planks replacement, flooring replacement, replastering, stone façade improvements, etc. As of now 85% of the work is completed and the target date of completion of the heritage building and concourse is December, 30, 2022 and the completion of the ticket counter is January 31, 2023,” a senior official said.