Updated On: 16 January, 2023 04:54 PM IST | Mumbai | mid-day online correspondent
The Western Railway said that the work was carried out as per sanctioned by the traffic work order of 34 days during which two new crossovers have been inserted at Points 154-155-156-157 (DOWN Local lines to DOWN Fast lines)

The trial of 30 kmph for both crossovers was conducted on January 11 and January 12
The Western Railway’s Mumbai Division on Monday said that the infrastructure work of insertion of crossovers at Andheri Yard was successfully completed.
In a press release, the Western Railway said that the work was carried out as per sanctioned by the traffic work order of 34 days during which two new crossovers have been inserted at Points 154-155-156-157 (DOWN Local lines to DOWN Fast lines). The trial of 30 kmph for both crossovers was conducted on January 11 and January 12.