Updated On: 07 December, 2023 06:58 AM IST | Mumbai | Rajendra B. Aklekar
Construction work on the bridge progresses despite hurdles; anticipated completion by mid-2024

Ongoing construction of the new east-west Vikhroli road over bridge
With the demolition and flattening of key commercial structures hindering the construction of the new east-west Vikhroli road over bridge on Tuesday, work should now proceed smoothly without any interruptions. Officials stated that 60 per cent of the physical work has already been completed, and the bridge is expected to be ready by mid-2024. “The bridge costs Rs 26.68 crore, divided equally between the state government and the railways, with the Central Railway contributing Rs 13.34 crore and the state government providing a matching sum,” said a senior official.
The bridge has faced immense delays due to land acquisition issues and the rehabilitation of project-affected people and structures. It has been 12 years since the closure of the level crossing gate in 2011, resulting in the loss of east-west connectivity for local residents of Vikhroli. Although there are east-west road bridges at Ghatkopar and Kanjurmarg stations, both a few kilometres away, residents of Vikhroli must take a detour to Ghatkopar or Kanjurmarg to travel from east to west or vice versa. While the arterial Lal Bahadur Shastri Marg is situated in the west, the Eastern Express Highway runs in the east.