Updated On: 06 December, 2022 06:00 AM IST | Mumbai | Rajendra B. Aklekar
MMRCL kicks off road restoration work at five stations; this is set to be completed by June 2023, when Line 3 will partially start operations; work on others will start soon, too

Barricades installed on the road for Metro Line 3 near BKC
Mumbai will soon get freedom from the grip of fences and temporary iron roads that the city’s first underground Mumbai Metro Aqua Line 3 had put up as it has announced completion of all tunnelling work and now is beginning restoration of roads. The Mumbai Metro Railway Corporation Limited has already kicked off road restoration work at five of its stations, with others planned up to be completed in a time-bound manner. MMRCL intends to complete the work of five stations and begin operations between Aarey and Bandra-Kurla Complex for Phase-I corridor by June 2023.