Updated On: 30 January, 2024 02:05 AM IST | Mumbai | Prajakta Kasale
Officials say they are on track for Feb 25 opening, even as residents raise concerns in Teli Gali work

BMC completed the concreting work on the Gokhale bridge on Monday
After declaring February 25 as the new deadline for the Gokhale bridge at Andheri, the Brihanmumbai Municipal Corporation (BMC) completed concreting the bridge on Monday. The curing period for the concrete is three weeks, and remaining work, including lighting, signage, lane marking, will be done simultaneously to complete it by February 23.
Meanwhile, in a follow-up letter to the BMC, residents raised the issue of the condition of the unused newly built Teli Gali flyover and the unfinished work of alignment of the Barfiwala bridge. The letter also mentioned that the girder for the second phase hadn’t arrived yet, despite the BMC’s assurance to open the whole bridge before the monsoon.