Updated On: 15 June, 2024 07:00 AM IST | Mumbai | A Correspondent
Initially slated for an October opening, CM Shinde ordered the opening of one of the connector bridges

The girder will connect the Coastal Road to the Bandra-Worli Sea Link
One of the connectors between the Coastal Road and the Bandra Worli Sea Link may open by the end of July. Initially, the arch bridges were scheduled to open by the end of October, marking the final stage of the Mumbai Coastal Road project.
The construction of the 10.5 km Coastal Road from Marine Lines to Worli is in progress. The BMC has already opened two sections, the southbound route from Worli to Marine Lines on March 11, and the northbound route from Marine Lines to Worli Lotus Jetty on June 10. These routes cover approximately 6.5 km. According to recent plans, the BMC intended to open the third phase from Nariman Point to Worli by July 10.