Updated On: 20 June, 2024 05:29 AM IST | Mumbai | Vinod Kumar Menon
Orders developer to execute agreement of sale with the buyers who only had with them allotment letters from pre-RERA period

The developer was ordered to execute the agreement of sale. Representation pic
MahaRERA has come to the rescue of flat buyers who were being arm-twisted by a developer to pay more to ink the agreements for sale for the flats booked far back as 2006. According to experts, this landmark order will benefit other flat buyers who endure long delays and unfair demands for payment by the developer. MahaRERA gave this order while deciding a bunch of complaints against a developer whose project at Goregaon, West has suffered prolonged delay.
The quasi-judicial body had recently passed an order in favour of 10 complainants, who only had allotment letters, some of which merely mentioned the floor and no mention of flat numbers.