Updated On: 27 July, 2021 11:26 AM IST | Mumbai | Rajendra B. Aklekar
Heavy rain had caused extensive damages in many areas, including the Karjat-Khopoli section; travellers upset over refunds due to cancellations

BEST team that has joined relief efforts in flood-hit Mahad
Days after rail traffic was disrupted on Central Railway, particularly the Karjat-Khopoli section, and the Konkan Railway due to heavy rain, services have resumed on both the lines.
Shivaji Sutar, CR’s public relations officer, said the Karjat area received 1,418.84 mm rain that battered the Bhor ghat two days ago resulting in extensive damages. “There were breaches at four locations for a total length of 150 metres and at seven locations ballasts washed away resulting in suspension of services on this section. Six overhead wire poles with foundations were damaged. Two digital circuits and four-point machines were also damaged,” he said.